This page provides a chronological overview of some of the primary project tasks (based on presumed start-dates; tentative dates are listed in parentheses). Where appropriate, the entry includes links to related documents, visuals, sources of additional information, public involvement opportunities, and other items of interest. Additional project activities will be added to this calendar as the project schedule is developed.



12 September 2005 Review records and establish list of Stakeholders, develop project website and GIS (maintain through end of project)
11 November 2005 Begin development of DRAFT CSM, Proposed DQOs and Initial Plans, TPP presentation materials, and Abbreviated Site Safety & Health Plan (SSHP)
22 December 2005 Coordinate with Stakeholders, mail meeting information
18 January 2006

TPP 1

Slide Show - 5.3 MB

The Technical Project Planning (TPP) process is designed to define and articulate the desired site closeout condition, and create a plan with the actions necessary to reach this goal, all with stakeholder acceptance. These initial meetings will bring a number of stakeholders together for an introduction to the site and project objectives and to begin the formal planning process. In conjunction with the first meeting, project team members will also conduct a site visit to develop familiarity with the current configuration of the project area.

23 January 2006 Based on input from stakeholders during TPP 1, development will begin on DRAFT versions of the RI/FS Workplan (and associated subplans), ESS, Safety Plan, and Public Invovlment Plan
15 February 2006

TPP 2

Slide Show - 19.2 MB

Changes to the initial plans will be communicated and feedback will be requested

27 March 2006 Submit Draft RI/FS, Safety and Public Involvement Plans to USACE for review
09 May 2006 Publish Draft Final RI/FS and Safety Plans and Final Public Involvement Plan
24 May 2006

TPP 3

Slide Show - 1.6 MB

Present DRAFT Work Plan and Public Involvement Plan to stakeholders and explain review process


Public Meeting 1

Slide Show - 4.8 MB

Initial presentation of project concepts and scope to the public


(back to top)

 Helpful Links
Contact Information
Links Page
Glossary of Terms
Acronym List
FAQ
Site Map
 Project Information
History
Current Activities
Schedule
Project Team
Safety
Documents
Maps
U.S. Army Corps of Engineers, LA District MARRS Services, Inc. Earthtech Global Environmental
© 2006 U.S. Army Corps of Engineers - All Rights Reserved